Vestas receives 202 MW order in the USA
Published: Wed, 2011-08-24 11:32Vestas has received a 202 MW order from E.ON Climate & Renewables North America for 112 V100-1.8 MW turbines for the USA.
The project’s name and specific location will be disclosed at a later date.
The contract includes delivery and commissioning along with a five-year service and maintenance agreement. Delivery is scheduled for the first half of 2012 and commissioning is expected in mid-2012.
“We are excited to again work with one of the leading wind-power operators in the world to move this project forward,” said Martha Wyrsch, President of Vestas-American Wind Technology, Inc. “E.ON chose a turbine that is specifically designed to capture the lower wind speeds of this area.”
Once finished, the project will provide enough electricity to power more than 60,000 American homes in a year. It also will create construction and turbine-maintenance jobs.